New Cross Substation.
Location New Cross, London
Sector Civils
Value £3M
The New Cross Substation is a critical component of National Grid's £1 billion London Power Tunnels 2 (LPT2) project, a major infrastructure upgrade designed to reinforce the capital's electricity network. This ambitious project involves the construction of new high-voltage transmission circuits and substations to meet the growing demand for electricity in London.
Gobion Construction, as a subcontractor to Linxon, played a crucial role in the project by executing the groundworks package, which is essential for the successful construction of the New Cross Substation.
-
Extensive earthworks, including excavation for the substation building, trenches for cables, and associated infrastructure.
-
Implementation of ground improvement techniques to ensure a stable foundation for the substation.
-
Installation of drainage systems to manage stormwater and prevent groundwater infiltration.
-
Coordination and execution of the diversion of existing utilities to accommodate the new substation.
-
Preparation of the site for subsequent construction phases, including leveling, compaction, and installation of temporary works.
Project Significance
The New Cross Substation is a vital component of the LPT2 project, contributing to the secure and reliable supply of electricity to London.
The project utilises advanced technologies and engineering practices to enhance the efficiency and resilience of the capital's electricity grid.
The successful completion of the groundworks package is crucial for the timely and efficient delivery of the entire substation project.
Technical Expertise
Gobion Construction demonstrated its technical expertise in executing complex groundworks operations, including:
Precise excavation techniques to minimise the risk of damage to surrounding infrastructure and utilities.
Effective ground stabilisation measures to ensure the long-term stability of the substation.
Efficient coordination with other trades to maintain a smooth and efficient construction process.
Safety and Compliance - Gobion prioritised safety throughout the project, adhering to all relevant safety regulations and implementing stringent safety protocols.
Project Delivery - Gobion successfully delivered the groundworks package on time and within budget, contributing to the overall success of the New Cross Substation project.